Germany’s Federal Network Agency has proposed a crisis core network that would use existing infrastructure to preserve basic mobile services during major disruptions. The aim is to maintain voice calls, emergency telephony and SMS when wider networks fail.
The proposal is contained in a strategy paper issued this week under existing Telecommunications Act provisions on security and network availability. It does not create binding obligations. Operators remain responsible for analysing their own networks, and any duties would be established through prescribed legal processes.
The Federal Ministry for Digital and State Modernisation helped prepare the paper with Deutsche Telekom, Telefónica Germany, Vodafone and 1&1 AG.
Berlin outages shape resilience plans
Two electricity outages in Berlin illustrate the scale of disruption behind the proposals. An arson attack on power pylons in the southeast of the city affected around 50,000 households and 2,000 businesses. A later cable bridge fire over the Teltow Canal affected around 45,000 households in southwest Berlin. Restoring electricity took 100 hours.
Power continuity sits at the centre of the agency’s recommendations for telecoms network resilience. The paper calls for expanded uninterruptible power supplies and emergency generators, with longer battery backup where proportionate. Network design, anticipated faults and cost-benefit analysis should determine the provision.
The recommendations also cover meshed networks, parallel nodes and multiple core data centres to maintain service after component failures. Mobile radio trailers can provide temporary coverage during repairs.
Fuel, access and asset records
Keeping generators supplied requires arrangements beyond the network itself. The paper calls for prioritised fuel deliveries and access through restricted zones for repair teams and contractors, including fallback procedures when access systems fail.
An asset registry forms the basis for selecting infrastructure for the crisis core network. Base-station coverage and emergency power records are central to that assessment, alongside radio technology, spectrum allocation and core network connections. The proposed network configuration must also track infrastructure changes. Sharing the necessary records across operators requires binding rules consistent with antitrust law, including safeguards for access, data minimisation and trade secrets.
Roaming, coordination and satellite limits
Emergency calls already have cross-network safeguards through limited service access. The paper identifies disaster roaming as a possible extension of those arrangements; the Telecommunications Act permits geographically-defined local roaming.
For incident coordination, the agency proposes a single coordination point and virtual situation centre to combine reports from authorities and operators in real time. Consolidated situation reports could replace separate reports about mobile backup equipment.
Direct-to-device satellite access appears in the paper as a medium-term complement to terrestrial networks. It is not presented as a replacement for strengthening ground infrastructure.
Operators cannot assume consistent satellite availability or connection quality in street canyons and indoor locations. Building interference, shadowing and unfavourable propagation constrain those connections and require technical or organisational measures.
Public safety and next steps
Public safety communications follow a separate programme. The paper proposes a long-term terrestrial broadband network alongside the existing TETRA digital radio system. In the short- and medium-term, BDBOS can pursue access to existing telecoms networks, particularly public providers’ networks.
The agency also plans a participation procedure to update emergency-call technical details under the Telecommunications Act. Entitled bodies will be invited through a gazette announcement to submit contributions and statements. DE-Alert follows a separate participation route.