An emergency order issued by the U.S. Department of Energy on Oct. 12, 2026, directing PJM Interconnection to draw on additional generating resources should be a wake-up call for Michigan and the rest of the grid operator's territory, according to a sponsored commentary by Terence Parker, a Michigan resident and member of the Solar Mounts LLC team.
The order, effective Oct. 13–16, authorizes specified power plants to operate as needed to maintain reliability and allows backup generators at large facilities to help reduce grid demand during emergencies. Parker wrote that the directive does not mean blackouts are inevitable, but it does highlight serious challenges facing the electricity system and the need to add capacity before emergency measures become routine.
Capacity prices and the cost of delay
Parker pointed to PJM's capacity auctions, where prices reached $329.17 per megawatt-day for the 2026–2027 delivery year and $333.44 per megawatt-day for 2027–2028, citing an analysis by Vicinity Energy. The later auction fell short of PJM's stated reliability requirement. Capacity costs are only one component of electricity bills, he noted, but rising prices signal growing pressure on consumers ahead of shortages that could force increasingly expensive emergency responses.
He also described the order's operational provisions: designated generating units may exceed specified operating limits when necessary for reliability, and PJM may direct backup generation at data centers and other large facilities, potentially including diesel generators as a last resort. Running fossil-fuel plants more frequently can increase emissions, he wrote, while diesel generators would add local noise pollution and expose operators to high diesel prices.
Winter outlook and the case for advance planning
NOAA's winter outlook, released Oct. 15, 2026, anticipates warmer-than-average conditions across much of the northern United States, including the Midwest, influenced by a strong El Niño. Parker argued that seasonal forecasts cannot predict every period of extreme demand, and that aging infrastructure, maintenance, changing weather and growing electricity consumption reinforce the need for advance planning rather than temporary authority to run additional fossil-fuel resources.
Solar, wind and storage timelines
Suitable solar projects may be built within 18 months depending on permitting, equipment and interconnection, whereas new nuclear facilities generally require substantially longer development periods, he wrote. Batteries can store surplus electricity for periods of higher demand. Parker added that faster interconnection reviews and better coordination among PJM, utilities, regulators, developers and state governments, alongside transmission upgrades, would bring capacity online sooner.
Farmland, siting and data center demand
Addressing concerns about solar on productive farmland in rural Calhoun County, where the company is based, Parker wrote that well-designed projects can include restoration plans allowing agricultural use to resume when leases end, and that leases can give farmers supplemental income when crop prices fail to keep pace with production costs. Agrivoltaic systems combine generation with compatible crops or livestock, he wrote, while parking lots, commercial properties, brownfields and landfills can also host solar, and carports provide electricity, shade and weather protection.
On data centers, Parker wrote that developers of new hyperscale facilities should demonstrate how they will secure adequate electricity and pay their fair share of supporting infrastructure through dedicated generation, renewable energy contracts, batteries, flexible demand or grid upgrades. Requiring every facility to build a gas-fired peaker plant is not necessarily the best answer, he added, because gas turbines face equipment and supply-chain constraints while additional fossil generation carries emissions and operating costs. Existing facilities should also cut peak demand where possible, with energy efficiency described as one of the most immediate options for businesses.